Outside Agency Construction Projects
PSEG Smart Meter Information
Please be advised that residential properties will be receiving letters from PSE&G in the near future informing them that PSE&G is going to begin deployment of smart electric meters in the City of Rahway. These meters will, among other things:
• provide you with more information about your electric use
• allow automatic, near real-time meter reading that will eliminate almost all estimated electric bills
• enable near real-time power outage detection and make storm restoration work more efficient
PSE&G has hired Contact Callers Inc (CCI) to perform the meter installations. Additional information regarding smart meters and their benefits is available at pseg.com/smartmeters as well as in the links below.
- General Project Documents
Elizabethtown (ETG) Pipeline Replacement Project
- General Project Documents
- Location Specific Documents and Information
- Washington Street Gas Main Construction Project - Fact Sheet
- Washington Street Map
Paving to begin: August 2024 Main Installation Projected Start - 9/11/2023 Projected Finish - 9/29/2023
Services & Retirement Projected Start - January 2024 Projected Finish- March 2024
Project limits are as follows: - Washington Street from Lawrence Street to Paterson Street - E. & W. Grand Ave - Paving Performed: 6/6/24 - 6/10/24
- E. Milton Ave Construction Project - Fact Sheet E. Milton Ave - Main Installation Projected Start - 6/6/2024 Projected Finish- N/A Services & Retirement Projected Start - August 2, 2024
- Washington Street Map
- Washington Street Gas Main Construction Project - Fact Sheet
- Lawrence St & Essex St Construction Project - Fact Sheet Lawrence St & Essex St - Main Installation Completed Projected Finish - N/A
Services & Retirement Projected Start - August 2, 2024 - Main Street Gas Main Construction Project - Fact Sheet Main Street - Main Installation Completed
Services & Retirement: Completed Paving to begin: August 2024 - E. Cherry Street - Main Installation Completed
Services & Retirement: Completed Paving to begin: August 2024